King Khalid International Airport (KKIA) Expansion Terminals 3 & 4 — Riyadh, Saudi Arabia

Actron Global delivered execution-led electrical and instrumentation support for ICTAS Saudi Arabia LLC as part of the King Khalid International Airport Development & Expansion Programme, contributing to the successful completion and commissioning of critical airport infrastructure systems.
Riyadh, Saudi Arabia
1970
Project Overview

Actron Global delivered execution-led electrical and instrumentation support for ICTAS Saudi Arabia LLC as part of the King Khalid International Airport Development & Expansion Programme, contributing to the successful completion and commissioning of critical airport infrastructure systems.

Scope of Work
  • Construction completion of airport electrical systems
  • Pre-commissioning and commissioning of MV switchgear and substations
  • MV cabling and branch wiring installation
  • LED lighting upgrades
  • Power integration for elevators, escalators, and moving walkways
  • UPS systems, earthing, and lightning protection
Project Context

The programme required the installation and integration of complex electrical infrastructure within a live airport environment.

Major electrical systems — including medium-voltage switchgear, transformer substations, lighting networks, and conveying system power integration — had to be delivered safely and in full compliance with KKIA operational standards. All works were executed while maintaining schedule certainty and minimising disruption to ongoing airport operations.

Project Snapshot
Client

Client

ICTAS Saudi Arabia LLC
Owner

Owner

KKIA
Sector

Sector

Aviation Infrastructure | Airport Expansion
Province

Province

Riyadh Province
Actron’s Role

Actron Global operated as a specialist execution partner supporting construction completion, pre-commissioning, commissioning, and start-up activities.

Our delivery teams provided hands-on technical oversight across MV installations, cabling, lighting upgrades, and system verification processes. Structured commissioning workflows ensured safe energisation, regulatory compliance, and seamless integration into live airport operations.

Energy-efficient commissioning practices and disciplined site coordination supported long-term system reliability, operational resilience, and performance continuity.

The Outcome

Electrical systems serving Terminals 3 & 4 and the terminal link were successfully completed, commissioned, and formally handed over.

The project demonstrates Actron Globals capability to deliver specialist technical execution within high-profile, operational aviation environments, maintaining strict compliance, safety discipline, and programme performance throughout.

Looking for embedded project management or technical consultancy support in Saudi Arabia?

Let’s discuss how Actron can strengthen your delivery performance.
  • Deep familiarity with Aramco GI/SAEP and site procedures
  • Multi-discipline manpower pipeline (Welding, Piping, Mech, E&I, Ops)
  • Safety-first culture — PTW/LOTO, audits & disciplined turnover dossiers

Trusted Partners

Safety First

Global Standards

bg

Talk to our team

Need a proposal or quick man power mobilization?

Integrated Technical Support Across the Full Project LifecycleIntegrated Technical Support Across the Full Project LifecycleIntegrated Technical Support Across the Full Project Lifecycle

Let’s Build Together

Ready to deliver your next project with precision, safety and speed?

Integrated Technical Support Across the Full Project Lifecycle
Integrated Technical Support Across the Full Project Lifecycle